Wingate Phase 2 (Overview)

Home / Projects / Wingate Phase 2 (Overview)

Project Update: Tuesday, February 26th, 2019

March 6 is now the date set for the first phase of the punch list walk through (final list of the small “end of job tasks” that need to be completed).  During the developer’s work through he will identify any items to be completed or corrected and set a schedule with the builder to take care of punch list items.

The property manager is now under contract and engaged. After vetting and meeting with several candidates Northern Realty Group Property Manager, Rebecca Robinson was selected.  The developers are extremely happy with Rebecca and her team.  She is a seasoned professional and very familiar with the Fort Worth area. She is already managing several high-end apartment complexes in the neighborhood.  Also, Rebecca understands that the exact location of our building is in an up and coming neighborhood which is extremely popular.  Marketing for pre-leasing will begin this coming week.

Work is also underway now on the syndication process and finalizing numbers.

Here’s a list of specifics in the construction process:

  • Balcony railings installed and painted
  • Blinds for all windows as well as balcony doors will be installed on Saturday March 2nd
  • Painting touch up currently underway
  • Electric service has been selected and engaged, meters are installed and permanent power to be active within a week
  • Mirrors have arrived and have been installed
  • Flooring is the next step and will be underway very soon
  • We’ve attached several photos of the current progress

While the building has taken longer than we all had planned, we know you will be pleased with the outcome! Your patience continues to be appreciated.

We thank you for being a part of this great project!

Project Update: Monday, December 24th, 2018

Firstly Jim and I would like to wish all our investors and their families a very Merry Xmas and best wishes for a great 2019.

For our Wingate investors, below is a list of current progress made in December:

  • Interior painting is well underway
  • Interior trim is installed
  • Interior doors installed
  • Interior trim and doors being painted
  • Cabinet installation is underway
  • Exterior brick work is nearly complete
  • Garage has been insulated
  • Garage drywall installation is nearly complete

The attached photos show details of these steps. Please feel free to reach out to Barry if you have any questions.

Here’s wishing you all a wonderful holiday!

DISCLAIMER: Quinlan MacKay is not a United States Securities Dealer or Registered Investment Adviser. Quinlan MacKay does not provide the purchase and sale of Registered Securities of any kind. This document and any other related documents are never to be considered a solicitation for any purpose in any form or content. If you are not the intended recipient of this document, you are hereby notified that any dissemination, distribution, copying, or action taken in relation to the contents of this and other documents received from Quinlan MacKay is strictly prohibited and may be unlawful. If you have received this document in error, please notify the sender immediately and permanently delete the original and any copy of this document and any printout.